EFYOS BLUE SMART A: organising packs and tapered insulation zones
When unloading SMART A, the assignment of the wedges to the plan must be preserved straight away. Packs split up without markings make later checking of the fall direction more difficult. Only the components needed for the current field should be brought to the installation position. The rest should be stored so that their type can be identified without unpacking the entire delivery. Before starting the scope described as a flat roof with tapered insulation and point drainage, it is worth establishing the unloading location and the sequence of execution. For EFYOS BLUE SMART A, the first important working point will be the lowest section of thermal insulation next to the outlet. The team should have a fall plan with markings for the individual wedges, not just a list of the materials purchased.