PIR insulation
Transport, cutting and storage of swissporPIR Alu
At a glance
swissporPIR Alu is a rigid PIR board whose core and thin facings can be damaged during improper handling. The condition of the packs, edges and surfaces must therefore be checked before installation. Damaged material is separated from boards ready for use, keeping the labels that allow the batch to be identified. A damaged edge profile should not be concealed by accidentally placing it in the insulation layer. The guide covers acceptance of the delivery, storage and the organisation of transport on site. Planning the storage location and the daily sections of work helps protect the material until it is covered. The product’s low thermal conductivity does not exempt it from checking its actual condition or from observing the storage conditions.

PIR boards from receipt to the point of use
Delivery of the PIR boards does not conclude the preparations, because damage to a corner can be concealed once further layers are installed. Before the material is distributed to the installation stations, the team checks the batch markings, photographs of the edges and the scope of elements requiring assessment together with the person supervising the works. This ensures that any non-conformity comes to light before the first stage.
Document parameters and the actual condition of the material
The parameters in the declaration relate to a product with a specific construction and thickness. For swissporPIR Alu, lambda is 0.022 W/(m·K), but the declaration must not be treated as permission for arbitrary storage conditions. On delivery and on the drawing, compare the local crushing of the swissporPIR Alu board with the declared lambda of 0.022 W/(m·K).
Before the first batch is used, the team relates the parameters of swissporPIR Alu to the actual condition and thickness of the material. Taping over the surface does not restore broken foam or lost support, so a visual assessment is not sufficient. The record states the actual thickness, the continuity of the core and the possibility of a correct connection with the adjacent board, so that the installed elements can be linked to the documents.
Polyurethane insulation requiring protection on site
swissporPIR Alu boards must be stored horizontally on level, hard supports, with a gap from the substrate. Protect them from sunlight, UV radiation and precipitation. Before installation begins, check the storage conditions and the condition of the material.
On the starting section, swissporPIR Alu is protected against water, sun and damage during transport, because the transport packaging is not a permanent roof over an exposed construction site. Accepting the starting section allows the condition of the edges and dry material to be preserved until installation. Before adding the next layer, the team records in the works documentation the storage location, the covering of the packs and the route for moving large elements.
Inspection after rainfall and before covering
Before installation, make sure that the boards are dry and undamaged; damp insulation must be replaced in accordance with the roof instructions. When completing the stage, check the dryness of swissporPIR Alu and the cleanliness of the cut joints before covering.
After rainfall, the team inspects the swissporPIR Alu boards on the laid section and cleans the edges before further covering. Damp insulation is replaced in accordance with the roof instructions instead of being enclosed in the assembly. The PIR foam in the board still requires protection, which is why dust is removed and the open edge is protected before work resumes.
Safe storage location for the batch
Before determining the storage location on the roof, check the load-bearing capacity of the structure and the method of securing against wind. A single board is light, but that does not mean that the entire stock of pallets can stand at one point. Before the next team enters the completed section, assess the location for temporary storage of swissporPIR Alu pallets.
The team checks the storage location for swissporPIR Alu for load-bearing capacity and protection against wind, because the low weight of a single board does not confirm that the entire stock can be placed at one point. The transport sequence is determined so as not to exert excessive pressure and not to damage the laid layers. On acceptance of the section, the unloading plan, the approved storage zones and the access routes are confirmed, and discrepancies are clarified before covering.
Insulation with polyurethane: deliveries in appropriate stages
Link the quantity of material to the daily progress of work and the possibility of closing the layers. Excessive stock on an exposed construction site increases the requirements for covering and moving. When accounting for the material, include the swissporPIR Alu delivery schedule linked to the closing of daily sections.
The quantity of swissporPIR Alu to be stored and covered in the planned stage is determined before the delivery is accounted for. Excess stock increases the protection requirements, while a shortage of a few elements stops completion of a fragment. The team limits unnecessary moving and downtime without risking the condition of the insulation, maintaining the division of batches, the order of taking boards and the acceptance deadlines before covering, so that later inspection does not rely solely on the number of pallets.
A case worth considering
After unloading, the team separates the packs of swissporPIR Alu requiring clarification from the batches ready for installation. Boards with damage are set aside instead of being pressed into a random place in the layer. Batch records and legible labels make it possible later to identify where a given material comes from. At the end of the shift, the remaining boards are secured so that the condition check before installation does not require searching the entire work front.
7 branches. Materials closer to your project.
- SEROCK — Dzierżenin 34 E
- BŁONIE — ul. Sochaczewska 138A
- RADOM — ul. Grobickiego 8
- ŁÓDŹ — Natolin 8
- OLSZTYN — Barczewo, ul. Prosta 9
- WROCŁAW — ul. Jerzmanowska 10C
- GORZÓW WLKP. — ul. Zielona 33/34